INDOOR GYM: State-of-the-art gym has a regulation basketball court and volleyball court, along with pulldown bleachers along the right-side wall and natural light pouring in from windows as long as the room.  A new Firehawk logo is on the floor at center court.

School’s Open!

By Eric Bazak, Editor-in-Chief
August 28, 2015
It took a year longer than expected to get the required permits, but once the first bulldozer clawed into the roof of the old building on June 6, 2014, construction never stopped.
SPIRAL: The new round foyer stretches from the entry level to the third floor.  The communal staircase emerges under a sunroof dome supported by beams that form the shape of a Jewish star.

Diverse spaces will become classrooms in ‘flexible’ new building, set to open in July

By Alexa Fishman, Editor-in-Chief
May 1, 2015
Boiling Point staffers who toured the construction site last Thursday saw the three-story lobby and grand staircase, reminiscent of government buildings in Washington DC. There are many windows and a domed skylight that let natural light into the lobby. Ironwork supporting the dome is in the shape of a Jewish star, which casts a six-pointed shadow on the lobby floor at midday.
GOING UP: View of new building from Olympia Medical Center parking lot March 11 shows the east side of Shalhevets new campus with, at center, red iron frame of the dome that will top the lobbys spiral staircase.

New building reveals its shape in views from parking structure

March 11, 2015
Windows, yellow insulation on east on south sides of new building are now visible from where teachers and students park at Olympia Medical Center
HIGHER: New support beams visible at the Shalhevet construction site rise to the level of the third-story floor, much higher than the building they are replacing.

At school construction site, a change in the skyline

By Rose Lipner, Community Editor
October 3, 2014

Rising two stories tall above the dirt and machinery, the first piece of Shalhevet’s building is now visible above the scaffolding...

SPACE: The now usable basement of the new building is bigger than expected, meaning more space available upstairs.

Foundation in place on Fairfax for new building

By Noah Rothman, Torah Editor
September 9, 2014

Shalhevet High School’s new building is growing—from the basement up. Trucks have been digging, workers building, and the...

Demolition has begun

Demolition has begun

By Alexa Fishman, Community Editor
June 6, 2014

At exactly 8:55 Friday morning, Shalhevet’s old campus started to come down, beginning with the Mansard-style roof over the...

HAZ-MAT: Visible above a specially covered dumpster, workers on the roof removed lead and asbestos May 12.

Cleanup will keep toxic dust where it belongs

By Noah Rothman, Torah Editor
May 28, 2014

What is behind that green fence? And why do there seem to be aliens in white space suits walking around on the roof of the...

QUESTIONS: Details like parking and location of some co-curriculars have yet to be ironed out.

Back to the future: Shalhevet will relocate to JCC during construction on new building

By Eric Bazak, Alexa Fishman, Noah Rothman, Features Editor, Community Editor, Torah Editor
May 21, 2014

UPDATED MAY 21 -- Going backwards to go forward, Shalhevet plans to relocate to the Westside Jewish Community Center for the 2014-2015...

DANGER: Workers remove asbestos, a toxic chemical that was formerly used to prevent fires, from the walls of the old school building April 29.  Asbestos must be removed first to prevent poison dust from being released when the building is demolished.

Shalhevet moving to JCC during construction, officials say

By Alexa Fishman, Community Editor
April 30, 2014

Shalhevet plans to relocate to the Westside Jewish Community Center for the 2014-2015 school year while its new building is under...

RAISE YOUR GLASS: Board treasurer Jeff Fishman drank some wine Thursday night on the day he signed papers closing the sale of Shalhevets building to Alliance Residential.  Rabbi Segal and board president Larry Gill were out of town.

Shalhevet closes building sale–finally

Ten months after construction was supposed to start and ending a series of delays caused by permit challenges from neighbors,...

Construction of new building now delayed until March

February 17, 2014

By Alexa Fishman, Community Editor Escrow closing on Shalhevet’s property sale has been postponed once again and now is slated...

UNANIMOUS: From left, Marsha L. Brown, Chanchanit Martorell and Franklin Acevedo of Central Area Planning Commission viewed slides before voting to overturn and appeal Shalhevets building project. the apartments shown are planned for the Southern part of the current campus which will vacated when Shalhevet moves into its new building on the Northern side.

Shalhevet wins construction appeal; demolition to begin within 60 days

By Noah Rothman, Staff Writer
December 13, 2013

The final appeal holding up construction for Shalhevet’s new building was overruled at City Hall downtown last Tuesday night,...